A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have…

The correct answer is D. Resource leveling. Resource leveling is a project management technique that involves resolving overallocation or scheduling conflicts to ensure a project can be completed with the available resources.

Tools and documentation

Question

A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

Options

  • ARisk identification
  • BGate review
  • CResource allocation
  • DResource leveling

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    4% (1)
  • C
    15% (4)
  • D
    74% (20)

Explanation

Resource leveling is a project management technique that involves resolving overallocation or scheduling conflicts to ensure a project can be completed with the available resources.

Topics

#resource leveling#schedule management#capacity planning#resource overallocation