The correct answer is C: Projects. According to PMI's standard portfolio management framework, a portfolio is a collection of projects (C) and programs (F) that are grouped together to facilitate effective management and alignment with strategic business objectives. A program is a group of related projects managed

Question

Which of the following make up a company's portfolio? (Choose two.)

Options

  • APeople
  • BProcedures
  • CProjects
  • DProcesses
  • EProfit
  • FPrograms

Explanation

According to PMI's standard portfolio management framework, a portfolio is a collection of projects (C) and programs (F) that are grouped together to facilitate effective management and alignment with strategic business objectives. A program is a group of related projects managed in a coordinated way. Both projects and programs are the components that constitute a portfolio. People (A), procedures (B), processes (D), and profit (E) are not the structural components that define a portfolio in project management terminology - though they may exist within the portfolio's context.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice