A project manager has been assigned a complex project and does not know all the activities required to complete it. Which of the following if the BEST approach to determine the work packages for the…

The correct answer is C. Bottom-up. What is the bottom-up approach to a project? The bottom-up approach to project management means that you begin with brainstorming possible solutions to meet that final deliverable. In other words, you know what the project goal is, but are not sure (yet) how to get there.

Tools and documentation

Question

A project manager has been assigned a complex project and does not know all the activities required to complete it. Which of the following if the BEST approach to determine the work packages for the WBS?

Options

  • ABrainstorming
  • BAnalogous
  • CBottom-up
  • DForward pass

How the community answered

(59 responses)
  • A
    15% (9)
  • B
    8% (5)
  • C
    73% (43)
  • D
    3% (2)

Explanation

What is the bottom-up approach to a project? The bottom-up approach to project management means that you begin with brainstorming possible solutions to meet that final deliverable. In other words, you know what the project goal is, but are not sure (yet) how to get there.

Topics

#WBS#work packages#bottom-up estimating#scope decomposition