PK0-004 Question #383: Real Exam Question with Answer & Explanation
The correct answer is D: Organizational chart. The scenario describes a matrix organizational structure, where team members report to both a functional manager and a project manager. To escalate an issue, the project manager must know who holds authority over that resource - which is shown in the organizational chart. The org
Question
Options
- AIssue log
- BRACI chart
- CRisk management plan
- DOrganizational chart
Explanation
The scenario describes a matrix organizational structure, where team members report to both a functional manager and a project manager. To escalate an issue, the project manager must know who holds authority over that resource - which is shown in the organizational chart. The organizational chart maps reporting relationships, hierarchies, and chains of command, identifying the correct escalation path. The Issue Log (A) records existing issues but does not show escalation paths. The RACI chart (B) defines roles and responsibilities on tasks but not the reporting/authority hierarchy. The Risk Management Plan (C) addresses risk responses, not resource escalation.
Community Discussion
No community discussion yet for this question.