CompTIA
PK0-004 · Question #360
A new corporate policy was approved that will positively affect the project. Which of the following should the project manager do FIRST?
The correct answer is A. Schedule the change. Change request - looks at the types of organizational change that can affect a project and the specific documents used in dealing with vendors.
Project life cycle phases
Question
A new corporate policy was approved that will positively affect the project. Which of the following should the project manager do FIRST?
Options
- ASchedule the change
- BReview the communication plan
- CUpdate the issue log
- DUpdate the risk register
How the community answered
(39 responses)- A82% (32)
- B3% (1)
- C5% (2)
- D10% (4)
Explanation
Change request - looks at the types of organizational change that can affect a project and the specific documents used in dealing with vendors.
Topics
#change management#positive change#schedule change#change request