The correct answer is C: Initiate a change request.. Always communicate the change first before implementing with project team.
Question
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following should the PM do NEXT?
Options
- ACrash the schedule.
- BNotify the project team.
- CInitiate a change request.
- DAccept the risk.
Explanation
Always communicate the change first before implementing with project team.