PK0-004 · Question #394

PK0-004 Question #394: Real Exam Question with Answer & Explanation

The correct answer is C: Initiate a change request.. Always communicate the change first before implementing with project team.

Question

A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following should the PM do NEXT?

Options

  • ACrash the schedule.
  • BNotify the project team.
  • CInitiate a change request.
  • DAccept the risk.

Explanation

Always communicate the change first before implementing with project team.