CompTIA
PK0-004 · Question #394
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following should the PM do NEXT?
The correct answer is C. Initiate a change request. Always communicate the change first before implementing with project team.
Project management concepts
Question
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following should the PM do NEXT?
Options
- ACrash the schedule.
- BNotify the project team.
- CInitiate a change request.
- DAccept the risk.
How the community answered
(37 responses)- A3% (1)
- B3% (1)
- C84% (31)
- D11% (4)
Explanation
Always communicate the change first before implementing with project team.
Topics
#change request#triple constraints#schedule compression#change control
Community Discussion
No community discussion yet for this question.