Given the information in the table below, which of the following is the total project cost?
The correct answer is B. $70,000. CEO Bonus and new executive admin are not part of the total project cost!
Project management concepts
Question
Given the information in the table below, which of the following is the total project cost?
Exhibits
Options
- A$40,000
- B$70,000
- C$95,000
- D$120,000
How the community answered
(33 responses)- A9% (3)
- B82% (27)
- C3% (1)
- D6% (2)
Explanation
CEO Bonus and new executive admin are not part of the total project cost!