PK0-004 · Question #374

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?

The correct answer is D. Temporary. A project is formally defined as a temporary endeavor undertaken to create a unique product, service, or result. 'Temporary' means it has a definite start and end date - in this case, starting in one week and ending at the 90-day delivery deadline. This is the key…

Project management concepts

Question

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?

Options

  • ARepetitive
  • BOngoing
  • CIterative
  • DTemporary

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    6% (2)
  • D
    88% (29)

Explanation

A project is formally defined as a temporary endeavor undertaken to create a unique product, service, or result. 'Temporary' means it has a definite start and end date - in this case, starting in one week and ending at the 90-day delivery deadline. This is the key distinguishing characteristic of a project versus ongoing operations. Repetitive (A) and Ongoing (B) describe operations, not projects. Iterative (C) describes a development approach or lifecycle type, not a defining characteristic of what makes something a project.

Topics

#project characteristics#temporary endeavor#project definition