PK0-004 Practice Questions
1,061 real PK0-004 exam questions with expert-verified answers and explanations. Page 7 of 22.
- Question #301
When would a project manager have a closure meeting? (Select THREE).
- Question #302
Before a change request is presented to the change control board, which of the following should the project manager do?
- Question #303
Which of the following should a project manager do for a team member who does not speak the same language?
- Question #304
A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of...
- Question #305
A conflict has developed among two project team members. The project manager reiterates the areas of agreement and avoids the areas of disagreement. Which of the following BEST des...
- Question #306
A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial. This would likely impact the project's:...
- Question #307
Which of the following information does the project risk register typically contain?
- Question #308
A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?
- Question #309
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
- Question #310
Which of the following documents ensures two parties do not share contractually binding information?
- Question #311
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Ta...
- Question #312
Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?
- Question #313
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale. Which of the following is the MOST like...
- Question #314
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project...
- Question #315
Which of the following documents serves the primary purpose of requesting details about a vendor's capabilities?
- Question #316
A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to p...
- Question #317
Which of the following is a characteristic of a project?
- Question #318
A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the p...
- Question #319
A project manager has been experiencing resistance from a group of stakeholders. With which of the following should the project manager consult to reduce friction going forward?
- Question #320
New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverab...
- Question #321
Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?
- Question #322
During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the bird's patterns. Lobbyists wo...
- Question #323
Which of the following features describe a projectized organization? (Select two.)
- Question #324
Which of the following are the BEST risk analysis tools to determine a project's risk level? (Select two.)
- Question #325
Which of the following are mutually binding project documents? (Select two.)
- Question #326
Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this is...
- Question #327
A new contractor joining the project team is an example of:
- Question #328
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering commi...
- Question #329
A primary work location is unsafe due to a gas leak. The project manager has implemented the business continuity plan and authorized relocation to an alternate site. Which of the f...
- Question #330
A PM is reviewing bids from vendors and has a question. Which of the following documents should the PM use to obtain a response?
- Question #331
A resource is assigned to two projects with two scheduled tasks that complete at the same time. This is known as:
- Question #332
A project has activities on the critical path that must be completed before other activities can start: Task A is dependent on Task C before Task D can be completed. Task A require...
- Question #333
Which of the following describes some of the features of the Agile methodology?
- Question #334
An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work. Which of the following types of procurement s...
- Question #335
Which of the following captures unforeseen activities throughout the project that need attention and resolution?
- Question #336
Which of the following project phases would MOST likely include a creating transition plan?
- Question #337
The Chief Executive Officer (CEO) has announced that the hardware division will be sold to another company. The sale of this division is an example of which of the following?
- Question #338
When closing a project, which of the following must be completed to allow team members to return to their designated departments?
- Question #339
A project manager has received numerous complaints from staff concerning poor service provided by a vendor. Which of the following steps should the project manager take FIRST to co...
- Question #340
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status. Which of the following types of reports should the pr...
- Question #341
A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The...
- Question #342
A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following st...
- Question #343
Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work. Which of the following management styles is the pro...
- Question #344
Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)
- Question #345
The project manager needs to motivate the team; however, is an insufficient budget for awards. Which of the following motivating agents is the MOST appropriate option the project m...
- Question #346
A project manager needs status on the project timeline. Which of the following team members should provide an update?
- Question #347
A project team is in the process of risk planning. One of the team members identifies a weather- related risk, which may cause delivery delays. Which of the following is the BEST r...
- Question #348
Under an Agile methodology, standup meetings occur:
- Question #349
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being de...
- Question #350
A project manager is required to maintain various documents and procedures. Which of the following require ongoing attention and periodic updates?