nerdexam
CompTIA

PK0-004 · Question #332

A project has activities on the critical path that must be completed before other activities can start: Task A is dependent on Task C before Task D can be completed. Task A requires Task B to start…

The correct answer is D. B, C, A, D. This question requires sequencing tasks on a critical path by satisfying all stated predecessor relationships. The correct order must place both B and C before A, and A before D.

Tools and documentation

Question

A project has activities on the critical path that must be completed before other activities can start:

Task A is dependent on Task C before Task D can be completed. Task A requires Task B to start. Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical path?

Options

  • AB, A, D
  • BC, B, D, A
  • CD, A, C
  • DB, C, A, D

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    33% (13)
  • C
    13% (5)
  • D
    50% (20)

Why each option

This question requires sequencing tasks on a critical path by satisfying all stated predecessor relationships. The correct order must place both B and C before A, and A before D.

AB, A, D

B, A, D omits Task C entirely, violating the dependency that C must precede A before D can be completed.

BC, B, D, A

C, B, D, A places D before A, directly violating the rule that A must complete before D can be completed.

CD, A, C

D, A, C places D first and C last, violating both the C-before-A and the A-before-D dependencies simultaneously.

DB, C, A, DCorrect

B, C, A, D satisfies every stated dependency. Task A requires Task B to start, so B precedes A. Task A is dependent on Task C before Task D can be completed, meaning C must also precede A, and A must precede D. Placing B and C first, then A, then D honors all constraints.

Concept tested: Critical path task dependency sequencing

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#critical path method#task dependencies#network diagram#scheduling

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice