nerdexam
ExamsPK0-004Questions#331
CompTIA

PK0-004 · Question #331

PK0-004 Question #331: Real Exam Question with Answer & Explanation

The correct answer is C: interproject resource contention. Interproject resource contention: Occurs when resources are assigned to more than one project resulting in timing and availability

Question

A resource is assigned to two projects with two scheduled tasks that complete at the same time. This is known as:

Options

  • Ashared resource contention
  • Bintraproject resource contention
  • Cinterproject resource contention
  • Ddedicated resource contention

Explanation

Interproject resource contention: Occurs when resources are assigned to more than one project resulting in timing and availability

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice