A resource is assigned to two projects with two scheduled tasks that complete at the same time. This is known as:

The correct answer is C. interproject resource contention. Interproject resource contention: Occurs when resources are assigned to more than one project resulting in timing and availability

Project management concepts

Question

A resource is assigned to two projects with two scheduled tasks that complete at the same time. This is known as:

Options

  • Ashared resource contention
  • Bintraproject resource contention
  • Cinterproject resource contention
  • Ddedicated resource contention

How the community answered

(26 responses)
  • A
    4% (1)
  • C
    92% (24)
  • D
    4% (1)

Explanation

Interproject resource contention: Occurs when resources are assigned to more than one project resulting in timing and availability

Topics

#resource contention#interproject conflict#resource management#scheduling