nerdexam
ExamsPK0-004Questions#308
CompTIA

PK0-004 · Question #308

PK0-004 Question #308: Real Exam Question with Answer & Explanation

The correct answer is C: Status report. The status report is the document that summarizes project progress at a point in time, including milestones reached and problems encountered, making it the primary reference for stakeholders.

Question

A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?

Options

  • AIssues log
  • BChange log
  • CStatus report
  • DMeeting minutes

Explanation

The status report is the document that summarizes project progress at a point in time, including milestones reached and problems encountered, making it the primary reference for stakeholders.

Common mistakes.

  • A. The issues log tracks only open problems and their resolution status, not milestone achievements or broader project progress.
  • B. The change log records approved and rejected change requests to scope, schedule, or cost, not general project events like milestones or problems.
  • D. Meeting minutes capture what was discussed and decided in a specific meeting, but they are not a consolidated project-level document that stakeholders use to review overall progress and events.

Concept tested. Project status reporting and stakeholder communication

Reference. https://www.pmi.org/learning/library/effective-project-status-reporting-7243

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice