CompTIA
PK0-004 · Question #308
PK0-004 Question #308: Real Exam Question with Answer & Explanation
The correct answer is C: Status report. The status report is the document that summarizes project progress at a point in time, including milestones reached and problems encountered, making it the primary reference for stakeholders.
Question
A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?
Options
- AIssues log
- BChange log
- CStatus report
- DMeeting minutes
Explanation
The status report is the document that summarizes project progress at a point in time, including milestones reached and problems encountered, making it the primary reference for stakeholders.
Common mistakes.
- A. The issues log tracks only open problems and their resolution status, not milestone achievements or broader project progress.
- B. The change log records approved and rejected change requests to scope, schedule, or cost, not general project events like milestones or problems.
- D. Meeting minutes capture what was discussed and decided in a specific meeting, but they are not a consolidated project-level document that stakeholders use to review overall progress and events.
Concept tested. Project status reporting and stakeholder communication
Reference. https://www.pmi.org/learning/library/effective-project-status-reporting-7243
Community Discussion
No community discussion yet for this question.