Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this issue?

The correct answer is B. Risks were not mitigated. When a risk response plan exists but safety concerns still arise due to non-adherence, the root cause is a failure to mitigate - meaning the planned risk reduction actions were not carried out.

Project management concepts

Question

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this issue?

Options

  • ARisks were not identified.
  • BRisks were not mitigated.
  • CRisks were not exploited.
  • DRisks were not communicated.

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    81% (21)
  • C
    8% (2)
  • D
    4% (1)

Why each option

When a risk response plan exists but safety concerns still arise due to non-adherence, the root cause is a failure to mitigate - meaning the planned risk reduction actions were not carried out.

ARisks were not identified.

Risks were clearly identified - the existence of a risk response plan proves identification had already occurred; the problem is not a failure to find the risks.

BRisks were not mitigated.Correct

Mitigation is the risk response strategy that involves taking proactive actions to reduce the probability or impact of a threat. If the risk response plan was not followed, the mitigation steps were not executed, leaving safety risks unaddressed and resulting in the observed safety concerns on the building project.

CRisks were not exploited.

Exploiting is a positive risk (opportunity) response strategy used to ensure an opportunity occurs; it is not applicable to safety threats or negative risks.

DRisks were not communicated.

While communication gaps can contribute to poor adherence, the question specifies the issue is non-adherence to the plan itself, pointing directly to a failure in executing mitigation actions rather than a communication breakdown.

Concept tested: Risk mitigation response strategy execution

Source: https://www.pmi.org/learning/library/risk-mitigation-strategies-project-management

Topics

#risk response plan#risk mitigation#safety management#risk monitoring