PK0-004 · Question #341

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The constraint…

The correct answer is C. scope. Halting a project due to shifting strategic priorities is a scope constraint because organizational strategy defines what work is authorized and in scope.

Project management concepts

Question

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The constraint described in this scenario is:

Options

  • Acost
  • Benvironmental
  • Cscope
  • Dscheduling

How the community answered

(19 responses)
  • B
    5% (1)
  • C
    89% (17)
  • D
    5% (1)

Why each option

Halting a project due to shifting strategic priorities is a scope constraint because organizational strategy defines what work is authorized and in scope.

Acost

Cost is not mentioned as a factor in this scenario; the project was halted because of strategic realignment, not budget limitations.

Benvironmental

Environmental constraints refer to external physical, regulatory, or ecological conditions, none of which are present in this scenario.

CscopeCorrect

Scope defines the authorized work and objectives a project is permitted to pursue, and organizational strategic priorities are the governing factor that determines whether that work remains in scope. When leadership redirects strategic focus, they are constraining or eliminating the scope of work the project is authorized to deliver. This is not a schedule or cost issue - it is a fundamental constraint on what the project is allowed to do, which is the definition of a scope constraint.

Dscheduling

Scheduling is not the constraint here because the team was explicitly ahead of schedule, meaning time was not the reason the project was stopped.

Concept tested: Project scope constraints and strategic priority alignment

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#project constraints#scope constraint#strategic priorities#project termination