PK0-004 · Question #342

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following steps of the control…

The correct answer is D. Evaluate impact and justification. Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed

Project life cycle phases

Question

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following steps of the control was missed?

Options

  • ACommunicate the change
  • BQuality check
  • CImplementation
  • DEvaluate impact and justification

How the community answered

(56 responses)
  • A
    2% (1)
  • B
    11% (6)
  • C
    5% (3)
  • D
    82% (46)

Explanation

Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed

Topics

#change control#impact assessment#change request process#change management