PK0-004 · Question #342
A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following steps of the control…
The correct answer is D. Evaluate impact and justification. Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed
Question
A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following steps of the control was missed?
Options
- ACommunicate the change
- BQuality check
- CImplementation
- DEvaluate impact and justification
How the community answered
(56 responses)- A2% (1)
- B11% (6)
- C5% (3)
- D82% (46)
Explanation
Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed