nerdexam
ExamsPK0-004Questions#312
CompTIA

PK0-004 · Question #312

PK0-004 Question #312: Real Exam Question with Answer & Explanation

The correct answer is A: SLA. The SLA is the binding document that specifies what the vendor must deliver and under what terms, making it the first reference when a vendor fails to meet project deliverables.

Question

Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?

Options

  • ASLA
  • BProject charter
  • CRisk register
  • DRFP

Explanation

The SLA is the binding document that specifies what the vendor must deliver and under what terms, making it the first reference when a vendor fails to meet project deliverables.

Common mistakes.

  • B. The project charter establishes project authorization and high-level goals but does not contain vendor-specific obligations or enforceable delivery terms.
  • C. The risk register tracks identified risks and planned responses but is not a contractual document and does not define vendor commitments or remedies.
  • D. The RFP is used during the procurement solicitation phase to invite vendor proposals and is not an enforcement instrument once a contract and SLA are in place.

Concept tested. SLA enforcement for vendor non-compliance in procurement management

Reference. https://www.pmi.org/learning/library/procurement-management-vendor-compliance-7946

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice