PK0-004 · Question #313
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale. Which of the following is the MOST likely reason the…
The correct answer is D. The project manager did not visit the project's international office locations. In a multinational project, the project manager's failure to physically visit international office locations eliminates access to the in-person, non-verbal cues that most reliably signal declining team morale.
Question
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale. Which of the following is the MOST likely reason the project manager would be unaware of the team member's decreased morale?
Options
- AThe project manager did not pay attention to visual cues.
- BThe project manager did not perform active listening.
- CThe project manager did not prioritize team member concerns.
- DThe project manager did not visit the project's international office locations.
How the community answered
(49 responses)- A12% (6)
- B6% (3)
- C4% (2)
- D78% (38)
Why each option
In a multinational project, the project manager's failure to physically visit international office locations eliminates access to the in-person, non-verbal cues that most reliably signal declining team morale.
The inability to observe visual cues is itself caused by not visiting the locations, making D the root cause rather than A being an independent failure.
Active listening enhances comprehension during direct interactions but cannot substitute for physical presence when team members are not communicating concerns through formal channels at all.
Failing to prioritize concerns would explain a poor response to morale issues that are already known, but it does not explain why the project manager had no awareness of them in the first place.
Morale is largely communicated through environmental and non-verbal signals - such as body language, informal conversations, and team dynamics - that are only directly observable during in-person visits. In multinational settings, team members across different cultures and hierarchies are often reluctant to report low morale explicitly through formal communication channels, so those signals go undetected remotely. Not visiting the international offices removes the project manager's only reliable opportunity to observe these interpersonal and environmental indicators firsthand.
Concept tested: In-person visibility gaps in multinational virtual team management
Source: https://www.pmi.org/learning/library/virtual-teams-global-project-management-6490