Question

A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale. Which of the following is the MOST likely reason the project manager would be unaware of the team member's decreased morale?

Options

  • AThe project manager did not pay attention to visual cues.
  • BThe project manager did not perform active listening.
  • CThe project manager did not prioritize team member concerns.
  • DThe project manager did not visit the project's international office locations.