PK0-004 · Question #314
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a…
The correct answer is B. Description, justification, and cost. A change request must include a description of the change, justification for why it is needed, and the associated cost to allow stakeholders to make an informed decision.
Question
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?
Options
- ADescription, cost difference of the replacement, and WBS
- BDescription, justification, and cost
- CCost difference of the replacement, justification, and communications plan
- DDescription, quality impact, and cost
How the community answered
(43 responses)- A2% (1)
- B95% (41)
- D2% (1)
Why each option
A change request must include a description of the change, justification for why it is needed, and the associated cost to allow stakeholders to make an informed decision.
The WBS is a project scope decomposition document and is not a standard component of a change request.
A change request requires a description of what is changing, a justification explaining why the change is necessary (in this case the component is unavailable), and the cost so approvers can weigh the financial impact. These three elements give decision-makers the information needed to approve or reject the request. The WBS and communications plan are separate project documents not included in a standard change request.
A communications plan governs how project information is distributed and is not a required element of a change request.
While quality impact may sometimes be noted, it does not replace justification, which is the essential element explaining why the change must occur.
Concept tested: Change request components in project management
Source: https://www.pmi.org/pmbok-guide-standards