nerdexam
CompTIA

PK0-004 · Question #314

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a…

The correct answer is B. Description, justification, and cost. A change request must include a description of the change, justification for why it is needed, and the associated cost to allow stakeholders to make an informed decision.

Tools and documentation

Question

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

Options

  • ADescription, cost difference of the replacement, and WBS
  • BDescription, justification, and cost
  • CCost difference of the replacement, justification, and communications plan
  • DDescription, quality impact, and cost

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    95% (41)
  • D
    2% (1)

Why each option

A change request must include a description of the change, justification for why it is needed, and the associated cost to allow stakeholders to make an informed decision.

ADescription, cost difference of the replacement, and WBS

The WBS is a project scope decomposition document and is not a standard component of a change request.

BDescription, justification, and costCorrect

A change request requires a description of what is changing, a justification explaining why the change is necessary (in this case the component is unavailable), and the cost so approvers can weigh the financial impact. These three elements give decision-makers the information needed to approve or reject the request. The WBS and communications plan are separate project documents not included in a standard change request.

CCost difference of the replacement, justification, and communications plan

A communications plan governs how project information is distributed and is not a required element of a change request.

DDescription, quality impact, and cost

While quality impact may sometimes be noted, it does not replace justification, which is the essential element explaining why the change must occur.

Concept tested: Change request components in project management

Source: https://www.pmi.org/pmbok-guide-standards

Topics

#change request#change documentation#cost justification#change description

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice