PK0-004 · Question #349

A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered. Which of…

The correct answer is C. Scope document F. Project plan. Ongoing requirement discovery causing rework and missed deadlines points to an incomplete scope document and a missing project plan to control execution.

Tools and documentation

Question

A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered. Which of the following are NOST likely missing from the project? (Select two.)

Options

  • AProject charter
  • BOrganizational chart
  • CScope document
  • DStatus report
  • EBusiness case
  • FProject plan

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    14% (5)
  • C
    75% (27)
  • D
    3% (1)
  • E
    3% (1)

Why each option

Ongoing requirement discovery causing rework and missed deadlines points to an incomplete scope document and a missing project plan to control execution.

AProject charter

A project charter authorizes the project at a high level but does not contain the detailed requirements or execution schedule needed to prevent rework.

BOrganizational chart

An organizational chart shows reporting relationships and does not address requirements completeness or schedule adherence.

CScope documentCorrect

A scope document (scope statement and WBS) defines the full boundaries of project work; without it, requirements continue to surface during execution, causing the rework described in the scenario. A well-defined scope prevents scope creep by providing a baseline against which change requests can be evaluated.

DStatus report

A status report tracks progress against existing plans but cannot fix the underlying absence of defined scope or an execution plan.

EBusiness case

A business case justifies the project's investment and is created before the project begins; it does not govern scope definition or task scheduling.

FProject planCorrect

A project plan establishes the schedule, resource assignments, and execution roadmap; without it, team members lack a structured timeline and accountability framework, which explains the failure to deliver tasks in a timely manner.

Concept tested: Scope definition and project planning artifacts

Source: https://www.pmi.org/learning/library/scope-management-plan-project-success-2642

Topics

#scope document#project plan#requirements management#missing documentation