The correct answer is C: Scope document. Ongoing requirement discovery causing rework and missed deadlines points to an incomplete scope document and a missing project plan to control execution.

Question

A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered. Which of the following are NOST likely missing from the project? (Select two.)

Options

  • AProject charter
  • BOrganizational chart
  • CScope document
  • DStatus report
  • EBusiness case
  • FProject plan

Explanation

Ongoing requirement discovery causing rework and missed deadlines points to an incomplete scope document and a missing project plan to control execution.

Common mistakes.

  • A. A project charter authorizes the project at a high level but does not contain the detailed requirements or execution schedule needed to prevent rework.
  • B. An organizational chart shows reporting relationships and does not address requirements completeness or schedule adherence.
  • D. A status report tracks progress against existing plans but cannot fix the underlying absence of defined scope or an execution plan.
  • E. A business case justifies the project's investment and is created before the project begins; it does not govern scope definition or task scheduling.

Concept tested. Scope definition and project planning artifacts

Reference. https://www.pmi.org/learning/library/scope-management-plan-project-success-2642