The correct answer is B: Release resources. Releasing resources is the formal closure activity that ends team members' project assignments and returns them to their home departments.
Question
When closing a project, which of the following must be completed to allow team members to return to their designated departments?
Options
- APerform retrospective
- BRelease resources
- CObtain sign-off from the sponsor
- DClose contracts
Explanation
Releasing resources is the formal closure activity that ends team members' project assignments and returns them to their home departments.
Common mistakes.
- A. A retrospective captures lessons learned for future improvement but does not formally return team members to their departments.
- C. Obtaining sponsor sign-off confirms formal project acceptance and completion but does not itself release team members back to their home departments.
- D. Closing contracts pertains to vendor and procurement agreements, not to the reassignment of internal team members.
Concept tested. Project closure resource release process
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok