Before a change request is presented to the change control board, which of the following should the project manager do?

Options

  • ASuggest the board study the cost of the change.
  • BEvaluate the affect on all other parts of the project.
  • CReview the change request with the project sponsor.
  • DRequest team member input on the value of the change.