nerdexam
CompTIA

PK0-004 · Question #344

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

The correct answer is D. Cost variance E. Earned value. Cost variance and earned value are the key earned value management (EVM) metrics that reveal actual performance deviations and guide corrective action planning.

Tools and documentation

Question

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

Options

  • APlanned value
  • BSchedule variance
  • CAcceptable variance
  • DCost variance
  • EEarned value

How the community answered

(46 responses)
  • A
    13% (6)
  • B
    7% (3)
  • C
    4% (2)
  • D
    76% (35)

Why each option

Cost variance and earned value are the key earned value management (EVM) metrics that reveal actual performance deviations and guide corrective action planning.

APlanned value

Planned value represents what was budgeted to be done by a point in time but alone does not indicate a problem without comparison to EV or AC.

BSchedule variance

Schedule variance is a valid EVM metric but the question asks for corrective action planning focused on problem areas, and the two best answers per the answer key are cost-focused metrics.

CAcceptable variance

Acceptable variance is a threshold concept used to define tolerances, not an analytical tool used to identify problem areas.

DCost varianceCorrect

Cost variance (CV = EV - AC) directly quantifies whether the project is over or under budget by comparing earned value to actual costs, making it a primary indicator for corrective action. When CV is negative, the project manager knows costs must be controlled.

EEarned valueCorrect

Earned value (EV) measures the budgeted value of work actually completed, serving as the foundation for all variance analysis and enabling the project manager to assess whether completed work aligns with the plan.

Concept tested: Earned value management metrics for corrective action

Source: https://www.pmi.org/learning/library/earned-value-management-best-practices-9999

Topics

#earned value management#cost variance#corrective action#schedule variance

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice