nerdexam
ExamsPK0-004Questions#316
CompTIA

PK0-004 · Question #316

PK0-004 Question #316: Real Exam Question with Answer & Explanation

The correct answer is C: Submit the request to the CCB.. To prevent scope creep, all change requests must flow through the formal Change Control Board (CCB) process regardless of who is requesting the change.

Question

A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep?

Options

  • ADeny the CEO's request.
  • BImplement the project change.
  • CSubmit the request to the CCB.
  • DAsk the CEO to follow the communications plan.

Explanation

To prevent scope creep, all change requests must flow through the formal Change Control Board (CCB) process regardless of who is requesting the change.

Common mistakes.

  • A. Flatly denying a CEO's request without a formal review process is inappropriate and bypasses the change governance structure.
  • B. Implementing the change without CCB approval is the definition of scope creep, as it adds work outside the approved scope baseline.
  • D. The communications plan defines how information is shared among stakeholders and does not govern how change requests are submitted or controlled.

Concept tested. Change control board process to prevent scope creep

Reference. https://www.pmi.org/pmbok-guide-standards

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice