PK0-004 · Question #328

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review…

The correct answer is C. Draft work breakdown structure. A project charter requires a draft work breakdown structure (WBS) to outline the high-level decomposition of project scope and deliverables.

Tools and documentation

Question

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:

Project description Draft project timeline and schedule Rough milestones Draft project budget Draft resources required High-level risk review Which of the following sections should be included in this document?

Options

  • ABusiness information
  • BFull risk assessment results
  • CDraft work breakdown structure
  • DFull resource requirements

How the community answered

(16 responses)
  • A
    6% (1)
  • C
    81% (13)
  • D
    13% (2)

Why each option

A project charter requires a draft work breakdown structure (WBS) to outline the high-level decomposition of project scope and deliverables.

ABusiness information

Business information is not a recognized standard section in a project charter; the project description already captures the necessary context.

BFull risk assessment results

A full risk assessment is too detailed for a project charter - the document appropriately contains only a high-level risk review at this stage, with detailed assessment occurring later in planning.

CDraft work breakdown structureCorrect

The project charter should include a draft WBS to provide a high-level structural decomposition of deliverables and work packages. All other standard charter components - timeline, milestones, budget, resources, and a high-level risk review - are already present, making the draft WBS the clear missing element that completes the document.

DFull resource requirements

Full resource requirements are too granular for a charter - the document already lists draft resources required, which is the correct level of detail for this early-stage document.

Concept tested: Project charter standard sections and components

Source: https://www.pmi.org/learning/library/charter-foundation-project-success-7347

Topics

#project charter#WBS#project initiation#planning documents

Community Discussion

No community discussion yet for this question.