nerdexam
CompTIA

PK0-004 · Question #347

A project team is in the process of risk planning. One of the team members identifies a weather- related risk, which may cause delivery delays. Which of the following is the BEST risk response…

The correct answer is C. Mitigate. Mitigating a weather-related delivery delay risk means taking proactive steps to reduce the probability or impact of that risk before it occurs.

Project management concepts

Question

A project team is in the process of risk planning. One of the team members identifies a weather- related risk, which may cause delivery delays. Which of the following is the BEST risk response strategy?

Options

  • AExploit
  • BEnhance
  • CMitigate
  • DCommunicate

How the community answered

(26 responses)
  • B
    4% (1)
  • C
    92% (24)
  • D
    4% (1)

Why each option

Mitigating a weather-related delivery delay risk means taking proactive steps to reduce the probability or impact of that risk before it occurs.

AExploit

Exploit is a response strategy for positive risks (opportunities), used to ensure the opportunity is realized; it is not applicable to a threat like weather delays.

BEnhance

Enhance is also an opportunity-focused strategy that increases the probability or impact of a positive risk, not a negative one.

CMitigateCorrect

Mitigation is the appropriate negative risk response strategy when a risk cannot be fully avoided but steps can be taken to reduce its likelihood or impact. For a weather-related delivery delay, mitigation actions could include building schedule buffers, using covered transport, or securing contingency suppliers. This strategy directly reduces the threat without requiring an opportunity to be leveraged.

DCommunicate

Communicate is not a formal risk response strategy in the PMBOK framework; it describes information sharing, not an action taken against the risk.

Concept tested: Negative risk response strategies - mitigation

Source: https://www.pmi.org/learning/library/risk-response-strategies-8cq9

Topics

#risk response#mitigation strategy#negative risk#weather risk

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice