A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this MOST likely a result? (Choose two.)
The correct answer is A. Business continuity response B. Resource changes. An immediate project relocation is most likely triggered by Business Continuity Response (A) and Resource Changes (B). Business continuity response covers situations where a team must move to maintain operations - for example, if a facility becomes unsafe or unavailable…
Question
Options
- ABusiness continuity response
- BResource changes
- CDisaster recovery response
- DRisk response
- EGate review
How the community answered
(31 responses)- A81% (25)
- C6% (2)
- D10% (3)
- E3% (1)
Explanation
An immediate project relocation is most likely triggered by Business Continuity Response (A) and Resource Changes (B). Business continuity response covers situations where a team must move to maintain operations - for example, if a facility becomes unsafe or unavailable. Resource changes refer to shifts in personnel, facilities, or equipment availability that force the team to a new location. Disaster recovery (C) typically involves restoring systems/data after an incident, not physical relocation. Risk response (D) is too broad and not the primary trigger for relocation. Gate review (E) is a formal milestone checkpoint, not a trigger for relocation.