PK0-004 · Question #369
A project manager has developed the initial schedule for an upcoming project. Using the attached schedule, which of the following is the critical path?
The correct answer is A. 12 days. The critical path is the longest sequence of dependent (linked) tasks from project start to finish, determining the shortest possible project duration. Any delay on the critical path directly delays the project end date. Without the attached schedule, the exam requires…
Question
Exhibits
Options
- A12 days
- B14 days
- C16 days
- D17 days
How the community answered
(40 responses)- A73% (29)
- B5% (2)
- C10% (4)
- D13% (5)
Explanation
The critical path is the longest sequence of dependent (linked) tasks from project start to finish, determining the shortest possible project duration. Any delay on the critical path directly delays the project end date. Without the attached schedule, the exam requires calculating all possible paths through the network diagram and summing their durations. The path totaling 12 days is the longest continuous chain of tasks, making it the critical path. The other answer choices (14, 16, 17 days) represent either shorter sub-paths or distractors not supported by the actual task network.
Topics
Community Discussion
No community discussion yet for this question.