PGMP Practice Questions
582 real PGMP exam questions with expert-verified answers and explanations. Page 10 of 12.
- Question #452Program Governance
After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquart...
Program Risk ManagementProgram GovernanceComponent Project OversightStakeholder Communication - Question #453Program Governance
Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company's sta...
Program GovernanceReporting StandardsProgram ComplianceStakeholder Engagement - Question #454Program Benefits Management
An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits...
Cost-Benefit AnalysisFunding JustificationBenefits RealizationProgram Governance - Question #455Strategic Program Management
A program management team is invited to a company's annual strategy planning session. The CEO discusses the mission and vision of the organization, and how the strategic plan will...
Strategic AlignmentProgram EstablishmentOrganizational VisionProgram Definition - Question #456Program Life Cycle Management
Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolution...
Issue ResolutionProgram OversightDecision FacilitationStakeholder Engagement - Question #457Program Benefits Management
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce...
Benefits ManagementProgram DocumentationProgram ArtifactsChange Management - Question #458Program Stakeholder Engagement
A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to ha...
Stakeholder ManagementConflict ResolutionProgram GovernanceDecision Facilitation - Question #459Program Procurement Management
A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determine...
Procurement ManagementQualified Seller ListRequest for ProposalProgram Lifecycle - Question #460Program Life Cycle - Definition Phase
A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the progr...
Program Scope ManagementProgram Scope StatementProgram Life Cycle - DefinitionProgram Deliverables - Question #461Program Stakeholder Engagement
A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
Program TransitionStakeholder EngagementBenefits RealizationProgram Life Cycle - Question #462Life Cycle Management
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment...
Program Management Information System (PMIS)Configuration ManagementProgram ToolsProgram Life Cycle - Question #463Program Life Cycle Management
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
Program Work Breakdown StructureProgram PlanningScope DecompositionResource Constraints - Question #464Program Life Cycle Management
A small, regional utility closes a customer rewards program and transitions it to operations. The executive sponsor and program manager are concerned about the impact on benefits r...
Program ClosureLessons LearnedKnowledge ManagementOrganizational Process Assets - Question #465Program Life Cycle Management
A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and develo...
Program ClosureExit CriteriaPost-closure SupportProgram Transition - Question #466Governance
An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependen...
Program GovernanceStakeholder EngagementDependency ManagementBenefits Realization - Question #467Benefits Management
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template...
Benefits ManagementProgram PlanningRegulatory ComplianceChange Management - Question #468Program Life Cycle
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next?
Program DefinitionProgram RoadmapProgram LifecycleProgram Initiation - Question #469Program Life Cycle (Planning)
The program manager of a multinational program must reconcile data including subject matter experts' labor hour estimates, and other direct resource hour estimates. In addition, th...
Program BudgetCost BaselineFinancial ManagementEstimating - Question #470Governance
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requ...
Stakeholder ManagementProgram GovernanceConflict ResolutionStrategic Alignment - Question #471Program Life Cycle
Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned in...
Program Transition ManagementOperational ReadinessProgram PlanningStakeholder Engagement - Question #472
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate informatio...
- Question #473Program Definition
A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter...
Program CharterProgram InitiationProgram DefinitionProgram Funding - Question #474Program Governance
A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address questions. The new country manager u...
Communication ManagementStakeholder EngagementRisk ManagementProgram Governance - Question #475Program Stakeholder Engagement
A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the cond...
Stakeholder EngagementCommunity RelationsCommunication PlanningAdvocacy - Question #476Program Stakeholder Engagement
A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engage...
Stakeholder EngagementProgram PlanningStakeholder AnalysisInfluence Mapping - Question #477Program Governance
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is he...
Program GovernanceChange ManagementBenefits RealizationDecision Making - Question #478Benefits Management
A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's head...
Program InitiationBenefits RealizationStrategic AlignmentProgram Definition - Question #479Program Life Cycle Management
After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager's supervisor recommends a list of pr...
Resource ManagementTeam SelectionSkill AssessmentProgram Staffing - Question #480Stakeholder Engagement
A company CEO meets with key customers to learn how they can be better served. After discovering that some executive team members disagree with each other, the CEO asks the program...
Stakeholder ManagementProgram InitiationProgram DefinitionStrategic Alignment - Question #481Program Life Cycle Management
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not b...
Program ClosureProgram Lifecycle PhasesTransition ManagementProgram Delivery - Question #482Strategic Program Management
At the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company's strategy. During t...
Strategic AlignmentProgram GovernanceChange ManagementProgram Prioritization - Question #483Benefits Realization Management
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request...
Benefits Realization ManagementProgram Change ControlProgram GovernanceProgram Performance Monitoring - Question #484Program Life Cycle Management
A sponsor decides that the business environment is unfavorable for continuation of a program. The sponsor asks that the program be closed. What items should be completed as part of...
Program ClosureProgram Final ReportLessons LearnedPerformance Assessment - Question #485Program Risk Management
A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that count...
Program Risk ManagementRisk Response StrategiesContingency PlanningCompliance Risk - Question #486Program Risk Management
You are the program manager for your organization and you are trying to determine the possible outcomes of a risk event. You're analyzing the risk event's worst case scenario, most...
Risk ManagementQuantitative Risk AnalysisMonte Carlo SimulationProgram Performance Domains - Question #487Strategic Program Management
The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?
Strategic alignmentProgram valueOrganizational strategyBusiness justification - Question #488Program Stakeholder Engagement
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance. To resolve this situation,...
Program Communications ManagementStakeholder EngagementProgram PlanningProcess Improvement - Question #489Program Lifecycle Management
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptanc...
Program DocumentationUser Acceptance TestingQuality ManagementTest Planning - Question #490Stakeholder Engagement
A company wants to perform a preliminary stakeholder analysis to assess a new program's support. What should the program manager develop?
Stakeholder ManagementProgram Stakeholder EngagementStakeholder AnalysisProgram Planning - Question #491Program Life Cycle
The chief executive officer (CEO) informs the program manager that the delivery date for project A must be compressed by two months to accommodate market needs. Project A relies up...
Program Change ManagementProgram Resource ManagementProgram Schedule ManagementProgram Delivery - Question #492Program Governance
A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer to which of the following?
Program ReportingProgram DashboardsStakeholder CommunicationPerformance Monitoring - Question #493Program Benefits Management
A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure...
Benefits Realization ManagementProgram ClosureTransition ManagementSponsor Role - Question #494Program Resource Management
In a program's definition phase, a program manager in country A is assigned to expand a restaurant chain into country B. The program manager creates the program team by identifying...
Program Resource ManagementResource AcquisitionTeam FormationProgram Definition Phase - Question #495Benefits Management
Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are...
Program Scope ManagementBenefits RealizationCost-Benefit AnalysisProgram Monitoring & Control - Question #496Program Stakeholder Engagement
A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not...
Stakeholder ManagementStakeholder Engagement PlanExpectation ManagementProgram Benefits Communication - Question #497Strategic Alignment
After a company's senior executive management meeting, the CEO issues a mandate to automate a new- client on-boarding process that would effectively eliminate the current, manual,...
Program CharterProgram InitiationProgram OutcomesStrategic Alignment - Question #498Program Life Cycle: Program Closure
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were reali...
Program ClosureLessons LearnedPost-ReviewBenefits Realization - Question #499Program Benefits Management
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Trackin...
Phase Gate ReviewBenefits ManagementProgram GovernanceProgram Performance - Question #500Program Life Cycle Management
A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by t...
Program ClosureLessons LearnedOrganizational LearningProgram Life Cycle Management - Question #501Benefits Management
What would prevent a program manager from completing program closure once a program has been completed?
Program ClosureBenefits ManagementBenefits RegisterProgram Life Cycle