Program Stakeholder Engagement
Question
During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects. What should the program manager do to address the situation?
Options
- AReview and update the detailed stakeholder list.
- BReview and update the stakeholder engagement plan.
- CExecute the component project's communications management plan.
- DUpdate the risk register.
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Program Communications#Stakeholder Engagement#Program Execution#Issue Resolution