nerdexam
PMI

PGMP · Question #581

A program manager takes over a global program from another program manager. Upon arriving on- site, the program manager immediately sees that stakeholders are upset, because of a lack of updates and c

The correct answer is B. Review the program communications management plan and stakeholder register.. When taking over a program with upset stakeholders citing lack of communication, the program manager must first understand two things: what communications should have been happening (the Communications Management Plan) and who the stakeholders are and their needs (the Stakeholder

Program Stakeholder Engagement

Question

A program manager takes over a global program from another program manager. Upon arriving on- site, the program manager immediately sees that stakeholders are upset, because of a lack of updates and communications about the program. What should the program manager do first?

Options

  • AReview the program governance plan and communication log.
  • BReview the program communications management plan and stakeholder register.
  • CReview the stakeholder engagement plan and stakeholder matrix.
  • DNotify the executive sponsor and update the program issue log.

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    75% (33)
  • C
    5% (2)
  • D
    14% (6)

Explanation

When taking over a program with upset stakeholders citing lack of communication, the program manager must first understand two things: what communications should have been happening (the Communications Management Plan) and who the stakeholders are and their needs (the Stakeholder Register). Option B provides both immediately. Option A includes the governance plan and communication log, which show what was planned and what was actually sent - useful, but the stakeholder register is more critical when the issue is stakeholder dissatisfaction. Option C reviews the engagement plan and matrix, which are useful for strategy but less foundational than identifying the stakeholders and communication requirements. Option D escalates to the executive sponsor before even understanding the situation - premature and potentially alarmist.

Topics

#Program Communications#Stakeholder Management#Program Transition

Community Discussion

No community discussion yet for this question.

Full PGMP Practice