nerdexam
PMIPMI

PGMP · Question #552

PGMP Question #552: Real Exam Question with Answer & Explanation

The correct answer is A: Prepare the stakeholder engagement plan for approval by the program steering committee.. See the full explanation below for the reasoning.

Program Stakeholder Engagement

Question

An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers. What should the program manager do first to obtain program approval?

Options

  • APrepare the stakeholder engagement plan for approval by the program steering committee.
  • BAnalyze the business environment to identify key stakeholders, and then perform a stakeholder
  • CConduct a brainstorming session with the program team to identify and analyze external
  • DCreate a project-level stakeholder analysis, and then perform a high-level program stakeholder

Topics

#Program Initiation#Stakeholder Engagement#Program Approval#Program Governance

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions