PMIPMI
PGMP · Question #552
PGMP Question #552: Real Exam Question with Answer & Explanation
The correct answer is A: Prepare the stakeholder engagement plan for approval by the program steering committee.. See the full explanation below for the reasoning.
Program Stakeholder Engagement
Question
An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers. What should the program manager do first to obtain program approval?
Options
- APrepare the stakeholder engagement plan for approval by the program steering committee.
- BAnalyze the business environment to identify key stakeholders, and then perform a stakeholder
- CConduct a brainstorming session with the program team to identify and analyze external
- DCreate a project-level stakeholder analysis, and then perform a high-level program stakeholder
Topics
#Program Initiation#Stakeholder Engagement#Program Approval#Program Governance
Community Discussion
No community discussion yet for this question.