nerdexam
PMI

PGMP · Question #551

A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives. What should the program manager do next?

The correct answer is A. Evaluate the impact of the new strategic objectives through a change request.. When a company acquisition introduces new strategic objectives mid-program, the program manager cannot unilaterally redirect the program - any significant change to scope, goals, or alignment must be formally evaluated through established change management processes. Choice A is

Strategic Program Management

Question

A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives. What should the program manager do next?

Options

  • AEvaluate the impact of the new strategic objectives through a change request.
  • BIntegrate the new acquisition into the program to include the new strategic objectives.
  • CAssess the impact of the new acquisition on the contract management plan.
  • DReview the benefits management plan to assess the continued validity of the program.

How the community answered

(38 responses)
  • A
    79% (30)
  • B
    5% (2)
  • C
    3% (1)
  • D
    13% (5)

Explanation

When a company acquisition introduces new strategic objectives mid-program, the program manager cannot unilaterally redirect the program - any significant change to scope, goals, or alignment must be formally evaluated through established change management processes. Choice A is correct because submitting a change request triggers the proper governance process: the impact of the new strategic objectives is assessed, documented, and escalated to the appropriate decision-making authority (steering committee, sponsor) who can approve, reject, or modify the program accordingly. Choice B assumes the acquisition should be integrated into the program, which is a significant decision that cannot be made without governance approval. Choice C narrows the analysis to only the contract management plan, missing the broader programmatic impact. Choice D (reviewing the benefits management plan) is a useful input to the change request analysis but is not the action - it is a step within the action.

Topics

#Strategic Alignment#Change Management#Program Governance#Organizational Strategy

Community Discussion

No community discussion yet for this question.

Full PGMP Practice