Strategic Program Management
Question
You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?
Options
- AA program is a collection of projects that work together to create one deliverable for the
- BA program is a collection of projects managed to gain benefits for the organization; the
- CA program is a uniform set of goals that are too large to be managed as one independent project
- DA program is a large collection of projects lead by a single project manager.
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Program Definition#Benefits Realization#Program vs. Project#Program Management Fundamentals