Which of the following is not a phase of program life cycle?

The correct answer is D. Program Planning. The PMI Standard for Program Management defines five phases of the program life cycle; Program Planning is not one of them. Planning activities are embedded within other phases such as Program Setup rather than existing as a standalone phase.

Program Life Cycle Management

Question

Which of the following is not a phase of program life cycle?

Options

  • AProgram Initiation
  • BProgram Closure
  • CProgram Setup
  • DProgram Planning
  • EDelivery of Program Benefits
  • FPre-program Preparation

How the community answered

(43 responses)
  • B
    2% (1)
  • C
    7% (3)
  • D
    88% (38)
  • F
    2% (1)

Why each option

The PMI Standard for Program Management defines five phases of the program life cycle; Program Planning is not one of them. Planning activities are embedded within other phases such as Program Setup rather than existing as a standalone phase.

AProgram Initiation

Program Initiation is a recognized phase in the PMI program life cycle where the program is formally authorized and the program charter is developed.

BProgram Closure

Program Closure is a recognized phase in the PMI program life cycle during which the program is formally concluded and resources are released.

CProgram Setup

Program Setup is a recognized phase in the PMI program life cycle during which the program infrastructure and governance are established.

DProgram PlanningCorrect

Program Planning is not a discrete phase in the PMI program life cycle; instead, planning activities occur within phases such as Program Initiation and Program Setup rather than constituting a separate phase of their own.

EDelivery of Program Benefits

Delivery of Program Benefits is a recognized phase in the PMI program life cycle during which component projects deliver their outputs and benefits are realized.

FPre-program Preparation

Pre-Program Preparation is a recognized phase in the PMI program life cycle during which the business case and program mandate are developed before formal initiation.

Concept tested: PMI program life cycle phases

Source: https://www.pmi.org/pmbok-guide-standards/foundational/program-management

Topics

#Program Life Cycle#Program Phases#Program Life Cycle Management