A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are

The correct answer is A. Program risk. During program initiation, high-level, strategic attributes are defined: the program's benefits (why it exists), its scope (what it will deliver), and its link to organizational strategy (how it aligns with business goals). Program risk, however, is identified and analyzed during

Program Life Cycle Management

Question

A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Options

  • AProgram risk
  • BProgram benefits
  • CProgram scope
  • DLink to organizational strategy

How the community answered

(22 responses)
  • A
    68% (15)
  • B
    18% (4)
  • C
    9% (2)
  • D
    5% (1)

Explanation

During program initiation, high-level, strategic attributes are defined: the program's benefits (why it exists), its scope (what it will deliver), and its link to organizational strategy (how it aligns with business goals). Program risk, however, is identified and analyzed during program planning - not initiation. Initiation focuses on establishing the program's justification and mandate, not the detailed risk identification that comes later in planning. Answer: A - program risk is the exception.

Topics

#Program Initiation#Program Definition#Program Management Phases#Program Lifecycle Management