PGMP · Question #469
The program manager of a multinational program must reconcile data including subject matter experts' labor hour estimates, and other direct resource hour estimates. In addition, the program manager mu
The correct answer is B. Component cost estimates. To establish a program baseline budget, the foundational input is the component cost estimates-the aggregated cost data from each program component (projects and non-project work). Labor hour estimates from SMEs and resource estimates roll up into component cost estimates, which
Question
The program manager of a multinational program must reconcile data including subject matter experts' labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis. Which of the following should be considered to get a baseline budget?
Options
- ACurrency exchange rates
- BComponent cost estimates
- CBaseline schedule
- DProgram payment schedules
How the community answered
(46 responses)- A4% (2)
- B93% (43)
- C2% (1)
Explanation
To establish a program baseline budget, the foundational input is the component cost estimates-the aggregated cost data from each program component (projects and non-project work). Labor hour estimates from SMEs and resource estimates roll up into component cost estimates, which are then consolidated into the program budget baseline. Option A (currency exchange rates) is an important consideration for a multinational program but is an adjustment factor, not the primary input. Option C (baseline schedule) informs timing of expenditures but is not the cost basis. Option D (payment schedules) governs cash outflows but relies on the cost estimates being established first.
Topics
Community Discussion
No community discussion yet for this question.