nerdexam
PMI

PGMP · Question #477

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a…

The correct answer is A. The program governance board. Program-level change requests that affect schedule and scope must be submitted to the program governance board, as they hold authority over program-level decisions.

Program Governance

Question

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Options

  • AThe program governance board
  • BThe program customer
  • CThe program management office (PMO)
  • DThe project governance board

How the community answered

(31 responses)
  • A
    77% (24)
  • B
    6% (2)
  • C
    3% (1)
  • D
    13% (4)

Why each option

Program-level change requests that affect schedule and scope must be submitted to the program governance board, as they hold authority over program-level decisions.

AThe program governance boardCorrect

The program governance board is the decision-making authority for changes that affect program scope, schedule, budget, or benefits realization. A change that extends the program schedule and requires a scope change is a program-level issue that requires governance board review and approval, not a decision the program manager can make unilaterally.

BThe program customer

The program customer may be a key stakeholder but does not have governance authority to approve changes to program scope and schedule.

CThe program management office (PMO)

The PMO provides support and standards but does not have decision-making authority to approve program-level scope and schedule changes.

DThe project governance board

The project governance board operates at the project component level and does not have authority over program-wide schedule and scope changes.

Concept tested: Program governance board authority for scope and schedule changes

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management

Topics

#Program Governance#Change Management#Benefits Realization#Decision Making

Community Discussion

No community discussion yet for this question.

Full PGMP Practice