PGMP · Question #464
PGMP Question #464: Real Exam Question with Answer & Explanation
Sign in or unlock PGMP to reveal the answer and full explanation for question #464. The question stem and answer options stay visible for context.
Question
A small, regional utility closes a customer rewards program and transitions it to operations. The executive sponsor and program manager are concerned about the impact on benefits realization. The program manager assures the executive sponsor that any corrective actions will be included in the next phase. What should the program manager do to ensure a successful transition?
Options
- AAsk each project manager to consolidate and file all program documentation in the corporate
- BObtain all project manager's contact information, and then have them reassigned back to their
- CAsk the program's business analyst to collect all project information and create a report.
- DEnsure that all program documents, including lessons learned, are archived in the knowledge
Unlock PGMP to see the answer