nerdexam
PMI

PGMP · Question #463

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

The correct answer is A. Decompose the program work based upon available resources. According to the PMI Standard for Program Management, a guiding principle for a program WBS is that the program manager decomposes work based on available resources. Unlike a project WBS (which goes down to the work package level), a program WBS is kept at a higher level and…

Program Life Cycle Management

Question

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Options

  • ADecompose the program work based upon available resources
  • BDecompose the program to the work package level
  • CDecompose the program to the architecture baseline level
  • DDecompose the program at a level sufficient to achieve control

How the community answered

(17 responses)
  • A
    71% (12)
  • B
    6% (1)
  • C
    18% (3)
  • D
    6% (1)

Explanation

According to the PMI Standard for Program Management, a guiding principle for a program WBS is that the program manager decomposes work based on available resources. Unlike a project WBS (which goes down to the work package level), a program WBS is kept at a higher level and structured around what resources can realistically execute. Option B is a project-level concept (work packages). Option C refers to architecture baselining, which is a specific technical activity. Option D, while sounding reasonable, describes a project management heuristic rather than the specific PMI program-level guidance on WBS decomposition.

Topics

#Program Work Breakdown Structure#Program Planning#Scope Decomposition#Resource Constraints

Community Discussion

No community discussion yet for this question.

Full PGMP Practice