PGMP · Question #463
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
The correct answer is A. Decompose the program work based upon available resources. According to the PMI Standard for Program Management, a guiding principle for a program WBS is that the program manager decomposes work based on available resources. Unlike a project WBS (which goes down to the work package level), a program WBS is kept at a higher level and…
Question
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
Options
- ADecompose the program work based upon available resources
- BDecompose the program to the work package level
- CDecompose the program to the architecture baseline level
- DDecompose the program at a level sufficient to achieve control
How the community answered
(17 responses)- A71% (12)
- B6% (1)
- C18% (3)
- D6% (1)
Explanation
According to the PMI Standard for Program Management, a guiding principle for a program WBS is that the program manager decomposes work based on available resources. Unlike a project WBS (which goes down to the work package level), a program WBS is kept at a higher level and structured around what resources can realistically execute. Option B is a project-level concept (work packages). Option C refers to architecture baselining, which is a specific technical activity. Option D, while sounding reasonable, describes a project management heuristic rather than the specific PMI program-level guidance on WBS decomposition.
Topics
Community Discussion
No community discussion yet for this question.