nerdexam
PMI

PGMP · Question #502

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, b

The correct answer is C. Recommend cancellation of the program based on performance metrics.. When a program can no longer deliver its planned return-on-investment within an acceptable level and the intended benefits have not been realized, the program manager's responsibility is to surface this reality to the governance board and recommend cancellation. A program's funda

Program Governance

Question

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on- investment within an acceptable level and the intended benefits have not yet been realized. After further analysis of the performance indicators, the program manager should do which of the following?

Options

  • AExtend the schedule to reduce costs and resource utilization.
  • BExpand the scope and continue the program until return-on-investment objectives can be met.
  • CRecommend cancellation of the program based on performance metrics.
  • DTransition the existing program results to the appropriate operational area.

How the community answered

(33 responses)
  • A
    12% (4)
  • B
    6% (2)
  • C
    55% (18)
  • D
    27% (9)

Explanation

When a program can no longer deliver its planned return-on-investment within an acceptable level and the intended benefits have not been realized, the program manager's responsibility is to surface this reality to the governance board and recommend cancellation. A program's fundamental purpose is benefits realization; if that is no longer achievable, continuing the program wastes resources and money. Option A (extending the schedule) would not fix the ROI problem and would likely increase costs further. Option B (expanding scope) would compound cost overruns. Option D (transitioning results to operations) is reserved for when benefits HAVE been realized - not when the program has failed to deliver them. The performance data clearly shows the program is not viable, making cancellation the appropriate recommendation.

Topics

#Program Governance#Benefit Realization#Program Performance#Program Termination

Community Discussion

No community discussion yet for this question.

Full PGMP Practice