nerdexam
PMI

PGMP · Question #466

An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business

The correct answer is C. Review and clarify the business team's program roles and responsibilities; determine the. Before escalating or restructuring, the program manager should first review and clarify the business team's program roles and responsibilities. This foundational step ensures everyone understands their obligations and identifies where gaps or misalignments exist. Escalating to th

Governance

Question

An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks. To address this issue, what should the IT program manager do next?

Options

  • ASchedule a meeting with the business team to discuss transferring the two business team
  • BEscalate the lack of commitment by the business team to the program steering committee;
  • CReview and clarify the business team's program roles and responsibilities; determine the
  • DModify the program milestone dates to include a larger contingency; determine the impact on

How the community answered

(30 responses)
  • A
    17% (5)
  • B
    7% (2)
  • C
    47% (14)
  • D
    30% (9)

Explanation

Before escalating or restructuring, the program manager should first review and clarify the business team's program roles and responsibilities. This foundational step ensures everyone understands their obligations and identifies where gaps or misalignments exist. Escalating to the steering committee (Option B) is premature without first establishing clarity on roles. Transferring resources (Option A) requires authority the IT program manager may not have. Adjusting milestone dates (Option D) treats the symptom rather than the root cause-unclear accountability. Clarifying roles is the first corrective action aligned with proactive program governance.

Topics

#Program Governance#Stakeholder Engagement#Dependency Management#Benefits Realization

Community Discussion

No community discussion yet for this question.

Full PGMP Practice