Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?
Options
- AProject managers
- BHans
- CProgram director
- DHans and each project manager
Unlock PGMP to see the answer