The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff.

The correct answer is B. Create a program communications management plan across all component projects.. The program manager's role is to establish program-level standards that govern all component projects. Creating a Program Communications Management Plan provides a single authoritative framework that all component projects - including the inexperienced Project B team - can align

Governance

Question

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff. What should the program manager do to ensure communications on the component projects are consistent?

Options

  • ARequest a more experienced project manager to work on project B.
  • BCreate a program communications management plan across all component projects.
  • CDirect all projects to use project A's communications management plan as a template.
  • DRework the communications management plans for all projects to be consistent.

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    73% (19)
  • C
    8% (2)
  • D
    4% (1)

Explanation

The program manager's role is to establish program-level standards that govern all component projects. Creating a Program Communications Management Plan provides a single authoritative framework that all component projects - including the inexperienced Project B team - can align to. Option A replaces a project manager rather than solving the systemic communications consistency problem. Option C uses Project A's plan as a template, which is informal and doesn't create a formal program-level governance artifact; it also assumes Project A's plan is appropriate for all contexts. Option D reworks all existing plans reactively - an inefficient approach when a single program-level plan can set the standard proactively from the top down.

Topics

#Program Communications#Program Governance#Consistency#Program Management Plan

Community Discussion

No community discussion yet for this question.