Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations…

The correct answer is B. Created a transition plan during the planning phase for the impacted operational area. Creating a transition plan during the planning phase is the foundational action that would have prevented this situation. A transition plan identifies all impacted operational areas, defines readiness requirements, establishes timelines for handoff, and ensures affected…

Program Life Cycle

Question

Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service, and is now unprepared and untrained to support the transformation. What should the program manager have done first to prevent this?

Options

  • AAdded the operations manager as a key stakeholder
  • BCreated a transition plan during the planning phase for the impacted operational area
  • CEnsured there was a communications management plan that included the transition to
  • DDrafted a training plan with assistance from the program management office (PMO) or human

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    78% (29)
  • C
    11% (4)
  • D
    3% (1)

Explanation

Creating a transition plan during the planning phase is the foundational action that would have prevented this situation. A transition plan identifies all impacted operational areas, defines readiness requirements, establishes timelines for handoff, and ensures affected departments are engaged and prepared well in advance. Option A (adding the operations manager as a stakeholder) supports engagement but alone does not ensure operational readiness. Option C (communications plan) ensures notification but not preparation or training. Option D (training plan) addresses one aspect of readiness but is a subset of the broader transition plan, which encompasses training, approval, and operational handoff in a structured way.

Topics

#Program Transition Management#Operational Readiness#Program Planning#Stakeholder Engagement