nerdexam
PMI

PGMP · Question #170

Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

The correct answer is A. Fallback plan. A fallback plan is the pre-planned alternative course of action implemented when the primary risk response strategy fails to be fully effective.

Program Life Cycle

Question

Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

Options

  • AFallback plan
  • BRisk response plan
  • CMitigation management plan
  • DMitigation plan

How the community answered

(65 responses)
  • A
    91% (59)
  • B
    3% (2)
  • C
    5% (3)
  • D
    2% (1)

Why each option

A fallback plan is the pre-planned alternative course of action implemented when the primary risk response strategy fails to be fully effective.

AFallback planCorrect

A fallback plan is specifically defined as an alternative set of actions and tasks prepared in advance for use when the selected risk response strategy does not adequately address the risk. It is triggered by a defined condition in which the primary strategy proves insufficient, providing the project manager with a ready response to residual or secondary risk exposure.

BRisk response plan

A risk response plan documents all planned responses to identified risks and is the primary strategy document itself - it is what fails to be fully effective, not the backup to it.

CMitigation management plan

'Mitigation management plan' is not a standard PMI-defined risk management document and does not appear in the PMBOK risk management framework.

DMitigation plan

A mitigation plan is a specific risk response strategy designed to reduce the probability or impact of a risk before it occurs - it is a primary response strategy, not the fallback when a strategy fails.

Concept tested: Fallback plan as secondary risk response when primary strategy fails

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Risk Response#Fallback Plan#Contingency Planning

Community Discussion

No community discussion yet for this question.

Full PGMP Practice