PGMP · Question #86

Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organizatio

The correct answer is C. Program transition agreement. The Program Transition Agreement is the formal document that defines how program deliverables, resources, and benefits will be transferred from the program to the organization (operations) at the conclusion of the program or at defined transition points. It establishes the terms,

Program Life Cycle

Question

Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

Options

  • AOperational transfer alliance plan
  • BProgram milestone list
  • CProgram transition agreement
  • DProgram scope statement

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    93% (37)

Explanation

The Program Transition Agreement is the formal document that defines how program deliverables, resources, and benefits will be transferred from the program to the organization (operations) at the conclusion of the program or at defined transition points. It establishes the terms, conditions, and responsibilities for the handoff. The program scope statement (D) defines what work is included. The milestone list (B) tracks schedule points. There is no standard artifact called an 'Operational Transfer Alliance Plan' (A).

Topics

#Program Transition#Program Closure#Program Artifacts#Benefits Realization