nerdexam
PMI

PGMP · Question #228

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

The correct answer is C. Secondary risks. Secondary risks are defined as new risks that arise directly as a result of implementing a risk response. For example, if you respond to a schedule risk by adding more resources, a secondary risk might be team conflict due to overcrowding. These must be identified, analyzed…

Program Life Cycle

Question

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

Options

  • AIn flux risks
  • BChain risks
  • CSecondary risks
  • DReactionary risks

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    93% (42)

Explanation

Secondary risks are defined as new risks that arise directly as a result of implementing a risk response. For example, if you respond to a schedule risk by adding more resources, a secondary risk might be team conflict due to overcrowding. These must be identified, analyzed, and managed just like any other risk. This concept is distinct from residual risks, which are risks that remain after a response has been applied. 'In flux risks' (A), 'chain risks' (B), and 'reactionary risks' (D) are not recognized project management terminology.

Topics

#Risk Management#Risk Responses#Secondary Risks#Program Risk

Community Discussion

No community discussion yet for this question.

Full PGMP Practice