You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and

The correct answer is D. Stakeholder identification. Stakeholder identification is a planning and initiating activity, not a monitoring and controlling activity. You identify stakeholders early in the program to understand who has an interest or influence in the program. Monitoring and controlling is concerned with tracking the ong

Program Life Cycle

Question

You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

Options

  • AMaterials required by the program
  • BEquipment your program uses
  • CSusan the application developer in your program
  • DStakeholder identification

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    7% (2)
  • C
    3% (1)
  • D
    76% (22)

Explanation

Stakeholder identification is a planning and initiating activity, not a monitoring and controlling activity. You identify stakeholders early in the program to understand who has an interest or influence in the program. Monitoring and controlling is concerned with tracking the ongoing execution of the program - which includes materials (A), equipment (B), and personnel like Susan the developer (C), all of which are resources that must be managed throughout the program lifecycle. Stakeholder engagement is monitored, but stakeholder identification itself is a one-time (or periodic) planning task.

Topics

#Program Monitoring & Controlling#Program Life Cycle Management#Program Management Responsibilities#Stakeholder Engagement