nerdexam
PMI

PGMP · Question #229

Which of the following increases when one fast tracks the project?

The correct answer is B. Risk. Fast tracking is a schedule compression technique where activities that were originally planned sequentially are performed in parallel or with overlapping timelines. While this can shorten the schedule, it increases risk because overlapping dependent activities creates greater un

Program Risk Management

Question

Which of the following increases when one fast tracks the project?

Options

  • AResource
  • BRisk
  • CCost
  • DCommunication

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    92% (33)
  • C
    3% (1)

Explanation

Fast tracking is a schedule compression technique where activities that were originally planned sequentially are performed in parallel or with overlapping timelines. While this can shorten the schedule, it increases risk because overlapping dependent activities creates greater uncertainty - errors or changes in an earlier activity may require rework in the parallel activity. Fast tracking does not inherently increase overall cost (C) or resource usage (A) in the same direct way. While coordination needs may grow (D), increased risk is the defining and most significant consequence of fast tracking recognized in project management frameworks.

Topics

#Fast Tracking#Schedule Compression#Risk Management#Project Scheduling

Community Discussion

No community discussion yet for this question.

Full PGMP Practice