PGMP · Question #229
Which of the following increases when one fast tracks the project?
The correct answer is B. Risk. Fast tracking is a schedule compression technique where activities that were originally planned sequentially are performed in parallel or with overlapping timelines. While this can shorten the schedule, it increases risk because overlapping dependent activities creates greater un
Question
Which of the following increases when one fast tracks the project?
Options
- AResource
- BRisk
- CCost
- DCommunication
How the community answered
(36 responses)- A6% (2)
- B92% (33)
- C3% (1)
Explanation
Fast tracking is a schedule compression technique where activities that were originally planned sequentially are performed in parallel or with overlapping timelines. While this can shorten the schedule, it increases risk because overlapping dependent activities creates greater uncertainty - errors or changes in an earlier activity may require rework in the parallel activity. Fast tracking does not inherently increase overall cost (C) or resource usage (A) in the same direct way. While coordination needs may grow (D), increased risk is the defining and most significant consequence of fast tracking recognized in project management frameworks.
Topics
Community Discussion
No community discussion yet for this question.