nerdexam
PMI

PGMP · Question #183

Which of the following statements are true regarding the Monitoring and Controlling Program Risks process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Risk Monitoring and Control is an ongoing process for the life of the program. B. Planned risk responses should be continuously monitored for new and changing risks. C. Monitoring reduces the impact of risk by identifying, analyzing, reporting, and managing risks on a. A is true: risk monitoring and control is a continuous activity that persists across the entire program lifecycle, not a one-time event. B is true: even planned risk responses must be re-evaluated as the program evolves, since new risks can emerge and existing risks can change…

Program Risk Management

Question

Which of the following statements are true regarding the Monitoring and Controlling Program Risks process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • ARisk Monitoring and Control is an ongoing process for the life of the program.
  • BPlanned risk responses should be continuously monitored for new and changing risks.
  • CMonitoring reduces the impact of risk by identifying, analyzing, reporting, and managing risks on a
  • DIt is the process of selecting the most suitable response to reduce the threats to the program

How the community answered

(39 responses)
  • A
    92% (36)
  • D
    8% (3)

Explanation

A is true: risk monitoring and control is a continuous activity that persists across the entire program lifecycle, not a one-time event. B is true: even planned risk responses must be re-evaluated as the program evolves, since new risks can emerge and existing risks can change in probability or impact. C is true: monitoring reduces risk impact by systematically identifying, analyzing, reporting, and managing risks on an ongoing basis. D is false: selecting the most suitable response to threats describes the Plan Risk Responses process (response planning), not the monitoring and controlling process. Monitoring focuses on tracking identified risks, detecting new ones, and verifying that response plans are working - not on choosing responses.

Topics

#Program Risk Management#Risk Monitoring#Risk Control#Program Processes